Pile driving to continue through winter on new Hastings Bridge
Crews this week begin laying the foundation for the new Highway 61 Mississippi River bridge in HastingsBy: Katrina Styx, Hastings Star-Gazette, South Washington County Bulletin
Construction has begun on the new Hastings bridge, but it will still
be a while before there’s much to see. The pile driving process will
continue until March or April, said project coordinator Steve Kordosky.
Pile driving is the foundation-laying process for bridges. Crews have
to sink piles deep enough so that they’re embedded with enough
friction and resistance to hold up the weight of the bridge, said Mn/
DOT public affairs coordinator J.P. Gillach.
Forty of the 120 12-inch-thick ground improvement pilings are already
in place on the north shore, Kordosky said, and should be finished in
the next month.
“They hope to have those all driven by about Dec. 1,” he said.
Ground improvement piling will take some of the load off the widening
roadway, he explained. Without them, the new road would settle once
it’s built. In order to support the weight, they have to be placed
160 to 190 feet below the surface.
The next part of the project is driving larger piles into the river.
There will be 70 of those, each one 42 inches in diameter. Each one
will be placed 180 feet below the surface.
“The water came up on us a couple of times, and we’re hoping to maybe
get at it late this week, maybe next week,” Kordosky said.
Crews will drive three test piles and place test loads on them to
make sure they’ll be able to support the weight they’ll need to. Once
testing is completed, they’ll put in cofferdams (enclosures designed
to create a dry work environment) and start putting in the production
piles. That process is expected to last into March or April, Kordosky
said.
Once pilings are completed on the north bank, soil will be brought in
to compact the underlying earth before the roadway embankment comes
in. Crews hope to see that done before winter sets in.
“They want to get that in here while the weather’s still
cooperating,” Kordosky said.
The visual quality team is also working to narrow down the bridge
color. The team is narrowing down the choices to three, which have
not been released yet. VQT members will then take the colors out to
the public to get feedback and bring back what they hear to the full
team, which will then make a final decision. Visual quality work is
scheduled to be completed around the end of this year.
Anyone interested in learning more about the bridge project can
attend a Bridge Chat, hosted by Mn/DOT. This week’s chat will be held
from 8 a.m. to 9 a.m. Thursday, Nov. 11, at Dunn Bros. Other chats
will be held at 11 a.m. Monday, Nov. 15 and Dec. 20, at Benny’s Grill
and Coffee Shop; and at 9 a.m. Nov. 24 and Dec. 22, at Emily’s Bakery
and Deli.
Tags: area news, daily updates, news, hastings, traffic
More from around the web