Some SPP roadwork complete, more work starting this week

Email

St. Paul Park City Council member Jeff Swenson gave an update on the 2009 Street and Utility Improvement Project at the council's June 15 meeting.

Swenson said all roads west of Lincoln, including the underground sewer and water lines, hydrants and gate valves have been completed. Concrete curbing, driveway aprons and corner radius sections are also complete.